Project Title: AUTOMATION OF DISPOSAL OF WASTE DEICING FLUIDS
Technical Contact: L.
Robert Kimball and Associates
Contact Person: Richard
Holes, PE
Corporate Sponsor: University
Park Airport
Contact Person: Bryan
Rodgers
Team Name: Cheetah
Engineering
Team Members: Chad
Verbano, Kevin Yontosh, Shawn Warren, Steve Young, Spencer Shih
PROJECT SUMMARY:
The University Park Airport, which is owned and operated by The Pennsylvania State University, provides air service to customers throughout the Centre Region. During the deicing period, approximately October 15 through April 15, the Airport provides deicing services to the airline carriers to prevent in-air and on-ground ice buildup that could detrimentally affect aircraft performance.
The aircraft deicing process uses either propylene or ethylene glycol. Each material is considered to be industrial waste and The Pennsylvania Department of Environmental Protection mandates that the glycol be collected and disposed of properly to prevent damage to the nearby environment.
The image to the left represents the underground storage tanks.
The airport has a separate apron where each aircraft taxis to be deiced.
This apron is surrounded on the downstream side by a concrete channel that
collects the runoff and diverts it to a single inlet. During the deicing
season, the runoff is directed into two 10,000 gallon underground storage
tanks. The inlet to the tanks is controlled by a valve which must be manually
operated from the tank’s location.
The image to the left represents the above ground storage tank.
Once the fluid is in the storage tanks, it is pumped into a 500 gallon above ground storage tank by two submersible pumps located at the bottom of one of the tanks. The pumps force the fluid into a 4” force main located next to the aboveground storage tank. The aboveground storage tank is located in the rear of the ARFF building. The pump must be manually controlled and the controls are located on the ARFF building. Airport personnel must stand at the control panel and time the amount of time the pump is running to insure that the aboveground storage tank is not overflowed.
The airport has two options for disposing of the spent deicing fluid. First, the airport can load the material directly from the 4” force main into a truck and then deliver it to the Bellefonte sewage plant. Second, since the Airport is allowed to dispose of material into the sanitary sewage system, the airport attaches a hose from the standpipe to the aboveground storage tank. The material is then slowly metered into the sewage system at a rate of 250 gallons every 24 hours through the opening of a spigot.
The problems with the current setup are as follows:
| 1. The current process must be run manually and requires 4 man-hours
a week
which is not desirable. |
| 2. The hose from the standpipe to the aboveground storage tank is not desirable. |
| 3. The aboveground storage tank is not desirable. |
| 4. The open sewer clean out is not desirable. |
| 5. The valve that allows spent glycol to enter the underground
storage tanks must be
manually controlled from outdoors which is not desirable. |
The goal of this project is to automate the process that the airport uses to collect the spent deicing fluid. As part of this project, design drawings showing the layout of the new system will be prepared using AutoCAD. In addition, the technical specifications for any new equipment will be provided.
SPECIFICATIONS:
Critical Design Issues:
1. Dispose of approximately a total of 15,000 gallons of waste deicing
fluid from the underground
storage tanks to the sewer drainage system during
the winter season.
2. The airport is only allowed to input 500 gallons of waste deicing fluid over a 48-hour period.
a. The sewage treatment plant set this rate and the
fluid must be metered into the plant
at a constant rate.
b. Deicing fluid has a high Biological Oxygen Demand
(BOD), even in a diluted state.
Thus the fluid must be metered
in a at a continuous rate to avoid using all of the oxygen
in the plant and killing
bacteria that make the plant run properly.
3. Underground space below current above-ground storage tank is not available.
a. Due to the amount of piping and wiring currently
located in the region adjacent to the
sewage drain inlet, an underground-storage
tank is not an option.
PROPOSED SOLUTION:
Automate Existing System With Pressure Sensors and an Automatic Flow Meter Valve
Design Aspects and Requirements
| 1. The current above ground storage tank will be replaced with
a 1000-gallon concrete
double-walled tank. The tank will be wound with heating coils to prevent the fluids from freezing. |
| 2. There will be 3 main pressure sensors installed to automate the system. |
| 3. A pressure sensor will be installed at the bottom of the aboveground
storage tank to activate
the pump. |
| 4. A pressure sensor will be installed at the top of the aboveground storage tank to deactivate the pump. |
| 5. A third pressure sensor will be installed in the underground
storage tank as a safety alarm
to prevent the pump from running when the fluid level is too low. |
| 6. Additional alarms will be included as necessary. |
| 7. An automatic flow meter valve will be installed at the outlet
of the aboveground storage
tank to meter fluid into the sewer drainage system at the rate of 10 gal/hr. |
| 8. A backup pump will be installed in the underground storage tanks. |
| 9. Controls for the system will be located in the General Aviation terminal. |
This solution was considered the best because it utilizes the current
system at the airport, which will minimize the cost of the project for
the airport.